You are in the process of making project staff assignments. You have several candidates for a position on the project team that requires?

specific qualifications. All the candidates seem to meet the qualifications. You also consider personal interests, characteristics, and availability of these potential candidates. Which of the following is true?

A. You are considering the roles and responsibilities input of the Acquire Project Team process.

B. You are considering the staffing management plan input of the Develop Project Team process.

C. You are considering the organizational process assets input of the Develop Project Team

process.

D. You are considering the enterprise environmental factors input of the Acquire Project Team

process.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/10/07
naveed noor
par naveed noor , cargo agent , Etihad Airways

expectations of the role, clarify duties and set work

Muhammad Saeed Iqbal
par Muhammad Saeed Iqbal , Head , Head Office

You are considering the roles and responsibilities input of the Acquire Project Team process.

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: D

Explanation: The enterprise environmental factors input of the Acquire Project Team process considers elements such as personal interests, characteristics, and availability of potential team members.

 