Register now or log in to join your professional community.
Method Statement and JSA are the documents attached to the ITP. The ITP can be created base on the procedure written on the Methodology and Safety of site and people involve in the job.
1. Approved Shop Drawings
2. Materials Approval
3. Checklist
4-Specification Details .
*highlight list of items ,materials,tools ... in a checklist Doc must be verified when work completed .
*InspectionTest Plan
*sign checklist
inspection report formets.
1. USED RAW MATERIAL QUALITY
2. FABRICATED OVER MATERIALS.
3. TEST PRODUCT OUTPUT ACC TO R R AND STANDARDS.
I have 4 to 5 years experience in inspection of the fabricated steel , its mechanical testing . I have good idea of different type steel.
This is depend on the kind of the job.