Describe how the company evaluate and assess the hse risk associated with your work activity?

user-image
Question ajoutée par walid ettih , HSE COORDINATOR , OMV
Date de publication: 2017/10/09
Joselito Maglaqui
par Joselito Maglaqui , HSSE Systems & Assurance Engineer - Currently looking for a job , Shell Philippines / Brunel - Finished contract

There is a document called HEMP. Hazard and Effects Management Process, created during the early phase of the project. Identifies the hazards that could come up specially during the construction phase. This is somewhat of a brainstorming among all discipline representatives.