Every status meeting should have time allotted for Risk Monitoring and Control. Which of the following sentences is not true?

A. Risk identification and monitoring should occur throughout the life of the project.

B. Risk audits should occur throughout the life of the project and are specifically interested in measuring the team's performance in the Risk Identification and Risk Monitoring and Control processes.

C. Risks should be monitored for their status and to determine whether the impacts to the objectives have changed.

D. Technical performance measurement variances may indicate that a risk is looming and should be reviewed at status meetings.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/10/13
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: B

Explanation: Risk audits should be performed throughout the life of the project and are specifically interested in looking at the implementation and effectiveness of risk strategies.