A. The critical path technique is the same as PERT. B. It allows for looping and branching. C. It should never be compressed. D. It's the duration of all tasks with zero float.
D. It's the duration of all tasks with zero float.
C. it should never be compressed
Answer: DExplanation: You calculate the critical path by adding together the durations of all the tasks with zero float. The critical path can be compressed using crashing techniques.