The project schedule is used to determine all of the following except which one?

 A. Activity start dates

B. Cost estimates

C. Float times

D. Activity end dates

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/12/02

I think it's B. Project schedule is created when activities are identified, their durations (option D), estimates (options A) and dependencies (option C) are identified. Project schedule helps project manager to allocated activities on a calendar.

 