Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

The project schedule is used to determine all of the following except which one?

 A. Activity start dates

B. Cost estimates

C. Float times

D. Activity end dates

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/12/02
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: B

 Explanation: The project schedule determines the start and ending dates of activities, determines float times, generally shows resource assignments, and details the activity sequences and durations.

 

More Questions Like This