the shows. You are getting ready to write the project management plan and know that all the following are true regarding the PMIS, except for one. Which of the following is true?
A. The PMIS includes a change control system.
B. The configuration management system is a subsystem of the PMIS.
C. The PMIS is an automated system.
D. The PMIS is a tool and technique of the Scope Planning process
Answer: D
Explanation: The PMIS is a tool and technique of the Develop Project Management Plan process. It's one of the elements of the enterprise environmental factors, which is an input to the Scope Planning process.