Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
A. The project charter should be published under the project sponsor's name.
B. The project charter should be published under the name of the project manager.
C. The project charter should be published under the name of the project champion.
D. The project charter should be published under the name of a manager external to the project.
Answer: DExplanation: According to the PMBOK Guide, the project charter should be published by a manager external to the project but with sufficient power and authority to carry it off.
Thank you for the invitation
I agree the option A