Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

You are the project manger for Xylophone Phonics. It produces children's software programs that teach basic reading and math skills.?

You're performing cost estimates for your project and don't have a lot of details yet. Which of the following techniques should you use?

A. Monte Carlo analysis, because this is a modeling technique that uses simulation to determine estimates

B. Analogous estimating techniques, because this is a form of expert judgment that uses historical information from similar projects

C. Parametric modeling, because this is a form of simulation used to determine estimates

D. Bottom-up estimating techniques, because this is a form of expert judgment that uses historical information from similar projects

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/01/11
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B

Analogous estimating-also called top-down estimating-is a form of expert judgment. Analogous estimating can be used to estimate cost or time and considers historical information from previous, similar projects.