Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

You have been hired as a contract project manger for Grapevine Vineyards. Grapevine wants you to design an Internet wine?

 club for its customers. One of the activities for this project is the installation and testing of several new servers. You know from past experience it takes about hours per server to accomplish this task. Since you're installing new servers, you estimate this activity to take hours. Which of the estimating techniques have you used? A. Parametric estimating B. Bottom-up estimating C. Reserve analysis D. Analogous estimating

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/01/18
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: AExplanation: Parametric estimating multiplies a known element-such as the quantity of materials needed-by the time it takes to install or complete one unit of materials. The result is a total estimate for the activity. In this case, 10 servers multiplied by 16 hours per server gives you a 160-hour total duration estimate

Zaferullah Sharief, PMP®
par Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option A is the best choice.

Aneesh Shandilya
par Aneesh Shandilya , Manager/ Lead Electrical , Orpic

Option A - Parametric estimating uses an algorithm or formula that multiplies a known element-such as the quantity of materials needed-by the time it takes to install or complete one unit of materials.result is a total estimate for the activity. 

More Questions Like This