Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Which organization, the project manager has total control of projects?

 A. Projectized organization B. Balanced Matrix organization C. Weak Matrix organization D. Strong Matrix

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/01/24
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: AExplanation: Projectized organization: The project manager has total control of projects. Personnel are assigned and report to a project manager.

Zaferullah Sharief, PMP®
par Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option A is the correct choice.

More Questions Like This