Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

You have been assigned as a project leader and must first review the statement of work provided by the customer. Which of the following is most?

often overlooked? A. Customer-furnished equipment and facilities B. Long-lead procurement items C. Data item deliverables D. Other subcontractor interface requirements E. Customer-imposed milestones

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/01/24
Zaferullah Sharief, PMP®
par Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option C is the best anwers.

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C  ------------------------

More Questions Like This