Which of the following statements depicts the key difference between contract close-out and administrative closure?

 A. Contract close-out formalizes project completion. B. Contract close-out includes product verification.C. Contract close-out includes updating records with final results. D. Administrative closure includes procurement audits. E. None of the above.

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/02/08
shabeeb  madapatuparambil
par shabeeb madapatuparambil , HSE Officer , Dutch Foundations Co.LLL

C and E. C describes it the closeout of particular subjects

Mohammed Qaisar I PMP I MCIPS I MBA
par Mohammed Qaisar I PMP I MCIPS I MBA , Group Procurement Manager (Civil) , Al Ghurair Construction LLC

The answer must be B as before administrative closure, the product must be verified for its functionality and fulfilling the purpose for what it produced.

Robert Henri Drouin
par Robert Henri Drouin , West Coast Company Advisor , Moreau Industries

Contract close-out comes before administrative close-out.

Contract close-out formalize the completion of the project execution or part of it, pending on the matter the project is broken-down into a hole item or various partial items/phases, that can be closed-out one by one.

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. Contract close-out includes product verification.