Which of the following is illustrated by a resource histogram?

 A. The expected requirements for critical path activities. B. The expected resource usage by time period. C. The resource assignments by work package. D. The resource assignments by activities. E. All of the above.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/02/08
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. The expected resource usage by time period.