Which of the following are indicative of duration estimates?

 A. How many hours a resource will work on an activity. B. When an activity is expected to start. C. How many work periods an activity is expected to last. D. When an activity is expected to finish.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/02/14
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. How many work periods an activity is expected to last.

يوسف دمدوم
par يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Tank you for the invitation

I agree the option C