Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

In which of the following situations would the PERT method be applied most?

 A. When little experience exists on which to base estimated of activity duration. B. When knowledge of the interrelationships of activities are crucial. C. When there is limited knowledge regarding the cost estimation related to the project. D. When resource requirements are well defined.

user-image
Question ajoutée par Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co
Date de publication: 2018/02/21
Matthew Chukwumah  Ajuwa
par Matthew Chukwumah Ajuwa , Safety coordinator and Logistics , ALCON NIGERIA LTD(CONSTRUCTION) SHELL CONTRACTOR

B -when knowledge of the interrelationshipa activities are crucial

Muhammad Farooq
par Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co

A. When little experience exists on which to base estimated of activity duration.

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?