Which of the following actions are irrelevant when the critical path needs to be reduced by 35% on a project?

 A. Crashing time schedule. B. Paralleling activities. C. Adding resources. D. Eliminating float. E. All of the above.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/03/07
Zaferullah Sharief, PMP®
par Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option D is the best choice.

Jawad Hassan Khan
par Jawad Hassan Khan , country head , Bank of Khyber

Answer is "D"

To adopt the strategy  we can save/reduce the amount. 

AZHARUDDIN MOHAMMED
par AZHARUDDIN MOHAMMED , IT Assistant , Contact Center Company

Answer is D. Eliminating Float...

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. Eliminating float. -------------------