Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Which of the following should be archived upon completion of a project that involved significant procurement?

C. Financial records. -

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/03/14
Narendran Sivalingam
par Narendran Sivalingam , Sr. Mechanical Engineer , TARGET LLC

Important items / equipments procured for a project, that should be listed in the "Inventory Schedule" with all the required informations as noted below and will be the part of "Operation & Maintenance Manual" while handing over the project to the end user;

1. Maufacturer & Suppliers contact information

2. Items Description, Make & Model

3. Spare parts & Part List Diagram for ease ordering the item, when it requires replacement