Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
A. Crash the tasks with lowest cost. B. Crash the tasks with highest cost. C. Crash the non-critical tasks. D. Crash the critical tasks.
D. Crash the critical tasks.
Option D is the best choice.
The cost effective rule for shortening a project is crash the non-critical tasks.