Which of the following is the cost-effective rule for shortening a project?

 A. Crash the tasks with lowest cost. B. Crash the tasks with highest cost. C. Crash the non-critical tasks. D. Crash the critical tasks.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/03/14
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. Crash the critical tasks.

Zaferullah Sharief, PMP®
par Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option D is the best choice.

Abiodun Joda
par Abiodun Joda , office manager , Tola Joda Innovations

The cost effective rule for shortening a project is crash the non-critical tasks.