What is signified when a forward and backward pass indicates total float is equal to - 20 days?

 A. The project is estimated to be- days ahead of schedule. B. Two branches converge on a node. C. The critical path must be evaluated to determine actual slack time. D. Duration compression may be required to meet the original project scope. E. None of the above.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/04/04
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

D. Duration compression may be required to meet the original project scope.