Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Prior to heavy lifting, what is the most critical point concerned?

user-image
Question ajoutée par MANOJ KUNJAPPY , Senior Document Controller , Samsung Engineering Co. Ltd.
Date de publication: 2013/05/14
Mammdouh Krdi
par Mammdouh Krdi , project manager , AL Muntasser

prior heavy lifting need checking the weight befor taking a decision what the kind of lifting machine to use andthe minimum radius avialable and compar that with lifting machine radius with safty times

Utilisateur supprimé
par Utilisateur supprimé

Prior heavy lifting operation ensure;

You carryout a full risk assessment which include but not limited to the following; 

1/ The machine is certified to lift and shift the item

2/ The machine can and will handle the weight of the item

3/ There is a free access to site

4/ The site is free of obstacles (overhead cables, towers, bridges etc..) which may prevent the lift  

5/ The receiving platform is able to take the weight 

6/ Banksman is a must.

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?