A graphical display of accumulated costs and labor hours for both budgeted and actual costs, plotted against time, is called ?

A. Trend line. B. Earned value report. C. Percent completion report. D. Trend analysis. E. S curve.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/05/30
Donald Martin
par Donald Martin , Senior Quality Manager/Construction Quality Control System Manager , Parsons

The answer is a progress S-curve.

Saher Sadad Sayed Mahmoud Fahmy El Gamal
par Saher Sadad Sayed Mahmoud Fahmy El Gamal , Projects Manager , Egyptian International Co. for Decoration & Contracting (SARAYA – Al Alfy Group)

S Curve :

A graphical display of accumulated costs and labor hours for both budgeted and actual costs, plotted against time

Abdullah Muhammad
par Abdullah Muhammad , Civil Engineer , Royal Marvelous Swimming Pools and Landscaping L.L.C

It is S curve which present all situation of project progress with respect to project cost.

Rehana Obaid
par Rehana Obaid , ADMIN , EMIRATES EXPRESS BUSINESS MEN SERVICE AJMANFREEZONE

Sir plz help me i need urgent job

Florina Preda
par Florina Preda , Management Consultant, Project Manager , Independent

That would be a control chart used for monitoring a process performance and thus for identifying the variations. 

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

E. S curve. --------------------