Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Which of the following is NOT a characteristic of the Project Management Plan?

A. Must be approved by project sponsor B. A bar chart that shows the order of tasks and their resource assignments C. Formal, written communication D. Collection of subsidiary plans

user-image
Question ajoutée par Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co
Date de publication: 2018/05/31

Which of the following is not a characteristic of a project A. An established objective B. Outcome is unique C. Continuous D. A clear beginning and end E. Never been done before

Abdullah Muhammad
par Abdullah Muhammad , Civil Engineer , Royal Marvelous Swimming Pools and Landscaping L.L.C

I think option C is the answer, 

Muhammad Farooq
par Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co

Answer: BExplanation: The Project Management Plan is not a bar chart (or a Gantt chart). It's the collection of all of the planning documents you create through all of the knowledge areas within the five process groups. It describes how your project will handle all of the activities associated with your project wor

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?