Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
The sponsor is writing a project charter. She recalls that a previous project the company performed for another bank ran over budget because the team had underestimated the effort required to install the reinforced walls in the vault. The previous project manager had documented the details of the lessons learned from this project. Where should the sponsor look for these lessons learned? A. The company's organizational process assets B. The project records management system C. The project's work performance information D. The project's performance reports
Answer: AExplanation: Lessons learned from past projects are always part of a company's organizational process assets, and are usually stored in a process asset library. The other three answers are important project tools, but they're not where you find lessons learned.