Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
used in a final projec report to communicate the status of a project? A. Status of deliverables B. Scope baseline C. Lessons learned D. Variance information
Answer: BExplanation: The scope baseline is not a particularly useful thing once a project's done. A baseline is what you use to measure any changes to the project - whenever there's a change, you always want to compare it against the baseline. But once the project is done, the baseline isn't necessary any more.