Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

You're managing a project with a schedule performance index (SPI) of 1.07 and a cost performance index (CPI) of 0.94.?

How would you BEST describe this project? A. The project is behind schedule and over its budget B. The project is ahead of schedule and within its budget C. The project is behind schedule and within its budget D. The project is ahead of schedule and over its budget

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/07/04
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: DExplanation: When you're looking at CPI and SPI numbers, remember: lower = loser. If your CPI is below 1.0, then your project is over its budget. If the SPI is below 1.0, then the project is behind schedule. In this case, the project is ahead of schedule, since its SPI is above 1.0. But it's over its budget, because it's got a CPI that's below 1.0.

More Questions Like This