Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

My Contract is Lumpsum. The qty on BOQ is exceeding the quantity in drawing. How iam eligible to claim Variation.?

As my Contract is Lumpsum, Item Manhole : Depth in the BOQ ranges2 to3 m depth = No's . And when iam working the quantity is becoming No's in the same depth.Actually problem is with Tender Working. Now iam i eligible to claim4 no's as variation. And the next question is in the BOQ item4 to5 m depth is not there ,but on site it is coming,.then can i add a new Item as Variation.The complete Tender Quantity is being proved wrong in the BOQ with Tender Drawings....

user-image
Question ajoutée par IMTHIYAZ KHAN , CIVIL ENGINEER
Date de publication: 2018/07/15
Girish K Chetty
par Girish K Chetty , Joint Director , Indian Air Force

The difference can be brought out indicating the diffrence which is coming as compared to the drawing.

Financial implication needs to be submitted for future cnsideration, else the schedule of work can get affected.

More Questions Like This