Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

You need to determine when to release resources from your project. Which part of the staffing management plan will be most useful for this?

A. Training needs B. Resource histogram C. Recognition and rewards D. Safety procedures

user-image
Question ajoutée par Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co
Date de publication: 2018/07/18
Muhammad Farooq
par Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co

Answer: BExplanation: One of the most important elements of the staffing management plan is the timetable, which tells you who will work on what, and when they will be released from the project. One of the most common ways of showing the timetable is the resource histogram (or staffing histogram). That timetable will let you know exactly when you plan to release your project resources.

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?