Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
have communicated their final acceptance of the project. You are now meeting with your team to update the organizational process assets with a record of knowledge gained about the project to help future project managers with their projects. This is BEST described as: A. Project records B. Work performance information C. Lessons learned D. Project management information system (PMIS)
Answer: CExplanation: Lessons learned are some of your most important organizational process assets. At the end of every project, you sit down with the project team and write down everything you learned about the project. This includes both positive and negative things. That way, when you or another project manager in your company plans the next project, you can take advantage of the lessons you learned on this one.