While identifying risks for a new construction project, you discover that a chemical you are using on your building cannot be applied ?

in rainy conditions. You also learn that your project will be ready for the chemical application around the time when most of the rainfall happens in this part of the country. Since the project can't be delayed until after the rainy season and you need to make sure the building gets the chemical coating, you decide that your team will just have to work around the rain. This is an example of which strategy? A. Accept B. Exploit C. Transfer D. Mitigate

user-image
Question ajoutée par Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co
Date de publication: 2018/07/31
Muhammad Farooq
par Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co

Answer: AExplanation: This is an example of accepting a risk. The team can't do anything about the weather, so the project manager has accepted the fact that they could end up being delayed by it.