Your team has identified a risk with some of the chemicals you are using on your highway construction project. It is really difficult to mix?

them just right and, based on past projects, you've figured out that there's a high probability that about% of the chemical supply will be lost in mixing problems. You decide to buy an extra% of the chemicals up front so that you will be prepared for those losses and your project won't be delayed. Which response strategy are you using? A. Accept B. Mitigate C. Avoid D. Transfer

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/07/31
Sherif Shabaan
par Sherif Shabaan , Green Riyadh.. Site Civil Engineer , Al Fahd Company

   ...... The answer is B. Mitigate

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: BExplanation: By buying the extra chemical stock, you are mitigating the risk.