Which of the following is not true about the Project Charter?

A. It formally assigns the project manager B. Includes a high level milestone schedule C. It is always created by the project manager D. It contains external constraints and assumptions

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/08/08
Jomar Depone
par Jomar Depone , PROJECT MANAGER , R. DAN & CO., INC

Project Charter is not necessarily be done by the Project Manager but it identifies the level of authority of the Project Manager.

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: CExplanation: The Project Charter is often created without the project manager's involvement. Sometimes it is handed to the Project Manager by the sponsor or high level manager.