You are using a Pareto chart to examine the defects that have been found during an inspection of your product. Which process are you performing?

A. Scope Verification B. Perform Quality Planning C. Perform Quality Control D. Perform Quality Assurance

user-image
Question ajoutée par Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co
Date de publication: 2018/08/15
Muhammad Farooq
par Muhammad Farooq , QA-QC Manager , AL Bawani Contracting Co

Answer: CExplanation: Whenever you use any of the seven basic tools of quality to examine the results of an inspection of your product, you are performing Quality Control. If you were examining the process your company uses to build multiple projects, you would be performing Quality Assurance.