Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Which of the following BEST describes when you perform the Monitor and Control Project Work process?

A. As soon as every deliverable is completed B. Continuously throughout the project C. At scheduled milestones or intervals during the project D. At the end of every project phase

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/08/15
hatem labib
par hatem labib , Quality control manager , MISER consultant

__________________B_______________________

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: BExplanation: One of the most important things that you do as a project manager is to constantly monitor the project for changes, and take the appropriate action whenever you make a change. But changes don't happen on any sort of schedule - if they did, it would make project management a whole lot easier! That means you need to continuously monitor your project to figure out whether or not its plans and scope need to change.

subbaraman Ramaswamy Iyer
par subbaraman Ramaswamy Iyer , Freelance Consultant , OUB Singapore

Project work process is a complex activity which can be performed by Action or Fish bone diagram and it is better first to identify the critical path so that timing is optimized for finishing the project in the scheduled timing and also spare some time for maintenance of the project.

More Questions Like This