Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

You are managing a project with a total budget of $450,000. According to the schedule, your team should have completed 45% of the work by now.?

But at the latest status meeting, the team only reported that% of the work has actually been completed. The team has spent $, so far on the project. How would you BEST describe this project? A. The project is ahead of schedule and over its budget B. The project is behind schedule and within its budget C. The project is ahead of schedule and within its budget D. The project is behind schedule and over its budget

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/08/29
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: BExplanation: If you want to evaluate how the project is doing with respect to the schedule and budget, you need to calculate CPI and SPI. The first step is to write down the information you have so far: BAC = $450,000, planned % complete = 45%, actual % complete = 40% and AC = $165,000. Now you can calculate PV = BAC x planned % complete = $450,000 x 45% = $202,500. And you can calculate EV = BAC x actual % complete = $450,000 x 40% = $180,000. Now you have the information you need to calculate CPI and SPI. CPI = EV / AC = $180,000 / $165,000 = 1.09, which is above 1.0 - so your project is within its budget. And you can calculate SPI = EV / PV = $180,000 / $202,500 = .89, which is below 1.0 - so your project is behind schedule.

Muhammad Nadeem
par Muhammad Nadeem , Manager Administration , China state Construction Engineering Corporation

B the Project is behind schedue and within its budget.

 

hisham abu dagga
par hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thank you for the invitation

Agreed with the answer Mohammed Farouk

With greetings and appreciation

yes i completed i am hard working person

Utilisateur supprimé
par Utilisateur supprimé

Thanks Mrs.Lana for invite ;

Fully agree with Mr.M.Farook answer [complete details] !!!

 

Regards .

A. The project is ahead of schedule and over its budget

Eric Celestino
par Eric Celestino , electrical technician , Gedac Electric

must write and good detail how many percent cost of the project

Tuyizere Gideon
par Tuyizere Gideon , general cashier , Lemigo hotel

yes, I might do the task according to the discussion

More Questions Like This