Your team has recommended a change to the scope verification process. What's the first thing you should do?

A. Write up a change request. B. Tell your team that the process has already been decided and they should follow it. C. Analyze the change versus the Project Management plan to see what its impact will be. D. Implement the change.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/09/05
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: CExplanation: You may get a question on the exam that asks what to do when you encounter a change. You always begin dealing with change by consulting the project management plan.

hisham abu dagga
par hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

 

Thank you for the invitation

Agreed with your Answer

With greetings and appreciation