Deliverables are made by one team member that cannot be processed by another one. This already leads to timely rework and bad morale among team members. Which project management tool is most appropriate to deal with problems like this? A. Organization chart B. RACI matrix C. Communications management plan D. Work authorization system
work authorization system most deal with problem like this because to ensure the right work is done in the right order
Answer: D -----------------------