How should change management be planned for?

A. Changes are generally not predictable, therefore planning for change management cannot be sensible. B. Changes are a sign of bad planning. One should avoid changes during a project thus eliminating the need to manage them. C. Change management can be planned in a set of management plans or a specific change management plan. D. Planning for change management should be done while the various change control processes are being applied.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/10/23
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. Change management can be planned in a set of management plans or a specific change management plan.