A. Ensure that forecasts on work and costs are adhered to. B. Ensure that approved change requests are being executed. C. Ensure that rejected change requests are not getting executed by mistake. D. Avoid that so-called experts influence your project.
It is very important to consider stakeholder expectations and requirements.
C. Ensure that rejected change requests are not getting executed by mistake.