identified many risks, analyzed them and planned for risk response. It is now two months later. What should you not do? A. Ensure that they handle all risks to save you from project level risk monitoring and control. B. Make sure that the sub project managers monitor their project work for new and changing risks. C. Make sure that the sub project managers keep track of the identified risks and those on thewatchlist. D. Make sure that the sub-project managers monitor trigger conditions for contingency plans.
Make sure that the sub project managers keep track of the identified risks and those on thewatchlist
A. Ensure that they handle all risks to save you from project level risk monitoring and control.