Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

You are in the process of establishing a total cost baseline for measuring project performance. All of the following ?

are outputs of this process EXCEPT: A. Scope baseline B. Project funding requirements C. Activity cost estimates D. Requested changes E. Cost management plan updates

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/12/19
Saiyid Maududi-Oracle Applications Consultant
par Saiyid Maududi-Oracle Applications Consultant , Entrerprise Architect , US Technomatrix, Inc

Hi Team,

The Performance Measurement Baseline is a time–phased schedule of all the work to be performed, the budgeted cost for this work, and the organizational elements that produce the deliverables from this work. 

The Performance Measurement Baseline is really 3 baselines – Technical Schedule and Cost Technical , Schedule , and Cost.

It’s the deliverables that the customer bought. These deliverables contain the Business Value of the project. Connecting the Deliverables with the needed capabilities is the basis of a credible project execution process – then we can answer Why we are doing something.

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. Activity cost estimates ------------------