Which of the following process is used to identify project roles, responsibilities, and reporting relationships for project team member? A

. Acquire project team B. Activity resource estimation C. Human resource planning D. Develop project team

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2018/12/19
Maaw Ahmed
par Maaw Ahmed , مطور ويب، التشغيل،دعم فني , Master Group

I think better is B as activty resource estimting is process in which porject team carrefully compiles athrough lising to the resources that will be needed in completing a project.

Mohamed Aboelmagd
par Mohamed Aboelmagd , Project Manager , Bonyan Almdayen

Human resource planning, is the process to identify project roles and responseability

zoubir kermiche
par zoubir kermiche , إداري , القدس للدراسات

I think by using the plan of human resourece we can Identify the roles of eatch member in the team and his responsibilities, after that we can know the reporting relationtionships of them

Saiyid Maududi-Oracle Applications Consultant
par Saiyid Maududi-Oracle Applications Consultant , Entrerprise Architect , US Technomatrix, Inc

Psychologists and management theorists have devoted much research and thought to the field of managing people at work

• Important areas related to project management include:

  Motivation theories

  Influence and power o Effectiveness

Making the most effective use of the people involved with a project

Processes include: 

Human resource planning: identifying and documenting project roles, responsibilities, and reporting relationships

Acquiring the project team: getting the needed personnel assigned to and working on the project Developing the project team: building individual and group skills to enhance project performance

Managing the project team: tracking team member performance, motivating team members, providing timely feedback, resolving issues and conflicts, and coordinating changes to help enhance project performance 

Adam Ahmed
par Adam Ahmed , IT & Web Developer , Freelance

Basm allah alrahman alrahim

 

C. Human resource planning

 

 

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. Human resource planning -----------------

Abdul jaseer banglavu parambil
par Abdul jaseer banglavu parambil , SENIOR TRAVEL CONSULTANT , Comfort Travel Group

B. Activity resource estimation 

Subramanyam Rathnam
par Subramanyam Rathnam , Turbine Mechanic , Turbo Associated power services

Hai sir. Turbin Technician and genaretor Technician

yassine belkaid
par yassine belkaid , Tech Lead Frontend , Matious

Is it during the recruitment process? or a company with already project's team members set? because I didn't well get the purpose from the question.

alexander kascheev
par alexander kascheev , project director , ООО Ворскла Сталь

Оценка ресурсов деятельности

More Questions Like This