A. Performance measurement analysis B. Forecasting, variance management C. Cost change control system D. Cost aggregation E. Project performance reviews
Correct Answer is D.:Cost aggregation
I think Cost aggregating, through project management, using the tool of Control Estimates, will be the least, plus other choices available.
D. Cost aggregation - all other choices are helpful tool/ technique in the process.
D. Cost aggregation
THE ANSWER
D. Cost aggregation
D. Cost aggregation ........
D. Cost aggregation ------------------
The least one tool or technique for cost controller is (B.) Forecasting and Variance Management. Variance calculation provides knowledge of overspending of major KPI´s with respect to the cost baseline. Moreover, the forecasting allows management to know the impact on the overall project and initiate thoughts for the mitigation and recovery measurements.