Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
back office accounting, billing and administrative system. Your project team is in the process of implementing the technical work required for the project. However one of the stakeholders for your project is requesting variance changes to the project. Which of the following is the best approach to take the beginning of the project in order to manage the project? A. Add contingency reserves into overall project schedule to plan for any potential change requests B. Involve the stakeholder in the project as early as possible C. Contact the stakeholder's supervisor to request that the stakeholder's activities be limited to the agreed upon scope of he project D. Contact the stakeholder to dissuade him from submitting un necessary change reque
B. Involve the stakeholder in the project as early as possible