activities using the arrow diagramming method. In addition, your team has applied resource leveling and schedule compression techniques on the project schedule. Which actions should be performed NEXT: A. Obtain approval of schedule B. Obtain acceptance of completed project scope C. Develop activity resource requirements D. Initiate schedule change control E. Decompose the work packages into smaller components called schedule activities
Obtain acceptance of completed project scope
C. Develop activity resource requirements
A. Obtain approval of schedule