are you least concerned with during the process? A. Providing forecast to update current schedule information B. Comparing actual project performance against project management plan C. None of the choices are correct D. Assessing performance to determine whether corrective actions are necessary E. Monitoring and implementation of approved changes
C. None of the choices are correct