Which of the following processes involves analyzing activity sequences, activity duration, and resource requirements, ?

to develop the project schedule? A. Activity definition B. Schedule development C. Activity duration estimation D. Activity sequencing E. Scope definition

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2019/02/06
andre andre
par andre andre , On Site Sitemanager/Structural /Civil/Mechanical/Tank plate Erection. , Kanye Kanye Projects Africa.

E -Scope definition.

C -Activity duration estimation.

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

B. Schedule development ----------------