Which of the following statements are FALSE regarding the cost change control system? A. It provides information on the project

scope and cost performance, such as which budgets have been met and which are not. B. It should be integrated into the integrated change control system C. Integrated change control system D. It defines the approval level necessary for authorizing the changes E. It defines the procedures by which the cost baseline may be changes

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2019/03/06
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

A. It provides information on the project scope and cost performance, such as which budgets have been met and which are not.