You are in the process of monitoring the various project processes and their performance. Which of the following?

is the LEAST appropriate output of this process? A. Requested changes B. Recommended corrective actions C. Recommended defect repair D. Recommended preventive actions E. Project scope statement updates

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2019/03/06
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

E. Project scope statement updates